What's Left on Carpenters Grade Road Now That It's Two-Way Again

Inbound traffic is back on Carpenters Grade Road. Since Wednesday, October 21, drivers headed toward Maryville have used the road again instead of detouring to Cochran Road. The corridor isn't finished yet. There is new curb and gutter along stretches of the road. Fresh asphalt now smooths the transition at the Ludlow Drive intersection. New driveway entrances have been going in along the road. On the west side, a long graded strip is still being shaped and leveled to take its stone base.

That strip is the clearest sign of where the project stands. The City of Maryville says crews are still working on "remaining roadway and multi-use path improvements," sometimes with flaggers around equipment. The contract completion date is January 14, 2027. Drivers got the headline milestone in October. What's left is the work built for people on foot, for the intersection by the Marathon station and for the neighbors on Cochran Road who carried the detour traffic for most of a year.

How the Corridor Got Here

The widening has been on paper far longer than it has been under construction. It entered the Knoxville Regional Long Range Mobility Plan in 2009 with a horizon year of 2024. Gresham Smith was hired as the design consultant in March 2019. TDOT authorized construction on September 19, 2024, and Cleary Construction, Inc. was awarded the job. Work began March 17, 2025.

Construction then moved through three phases, and each one rerouted a different set of neighbors.

Phase What it changed Timing
Phase I Realigned Cochran Road at Raulston Road and closed Cochran at the Raulston end Began mid-June 2025, complete July 16
Phase II Closed Raulston Road between Carpenters Grade and the new Cochran intersection Followed Phase I; city maps list it as complete
Phase III Closed Carpenters Grade to northbound traffic and detoured it to Cochran Road Started in November 2025, ended with two-way traffic on Oct. 21, 2026

Phase III ran longer than first planned. Before it started, WATE reported that it would begin the week of November 10, 2025, and that the detour pattern would last about six to eight months. By June 1, 2026, the relocation of water and sewer lines was 100% complete and the road reconstruction had reached 60% as of April. Even so, crews were still sealing storm-drain structures and finishing drainage improvements in mid-October.

What the Remaining Work Adds Up To

At a 2025 public meeting covered by The Daily Times, Maryville Assistant City Manager Kevin Stoltenberg summed up the whole project:

"What we're doing is about is a 0.98 mile of Carpenters Grade Road and an additional 0.35 mile of Raulston Road that includes widening of the existing two-lane runs, that right now have two 11-ft lanes, curb and gutter and drainage improvements, adding a 10 foot wide multi-use path on the west side of the road, which is similar to a Greenway Trail, and lastly, a signalized intersection for Carpenters and Raulston."

Construction alone was put at $8.9 million, before design and right-of-way costs. The city's bid notice set the project limits from Raulston Road and Peterson Lane to Cochran Road, 1.33 miles in total. The reopened lanes cover the first item on Stoltenberg's list. The rest is still in progress through the end of the contract:

  1. The multi-use path. It runs 10 feet wide on the west side of Carpenters Grade. Crews were grading and leveling it through mid-October.
  2. The permanent signal at Cochran, Raulston, Peterson and Carpenters Grade. The city describes it as an installation for the end of the project.
  3. Curb, gutter, drainage and paving on the road segments that still need them.
  4. Repaving and restriping on Cochran Road, which the city agreed to pay for once Carpenters Grade carried two-way traffic again.

The Path Has Already Carried Cars

Some drivers have already been on the path without knowing it. During Phase III, southbound Carpenters Grade traffic stayed open by moving onto the multi-use path between Melrose Station and Barrington. Now that both directions are back in the rebuilt lanes, that strip can become what it was designed to be.

The city's description is a 10-foot walking and bike path on the west side of the road, part of a corridor upgrade meant to improve safety on a stretch that carries more than 11,000 vehicles a day through Blount County and Maryville. For comparison, the two lanes the project widened were each 11 feet, so the path is about as wide as one of the old travel lanes. In WBIR's coverage, Engineering and Public Works Director Brian Boone described the goal as a road that "works for both cars, trucks, walkers, joggers and bicycles."

Stoltenberg compared the finished path to a greenway trail.

The Four-Way Stop by the Marathon Gets a Signal

The intersection at the Raulston end has been changing since the first phase. In Phase I, crews moved a stretch of Cochran Road near the Marathon gas station east toward the tree line, so Cochran now meets Raulston farther from the old four-way stop. A new traffic signal is the last planned piece at that junction, and the city says the signal will "improve safety and traffic flow for Cochran Rd, Raulston Rd, Peterson Rd, and Carpenters Grade."

Four roads meet there, so the signal changes more drives than any other remaining item. It is also one of the last pieces scheduled. Until it is installed, plan for the intersection to keep working the way it does now.

Cochran Road Gets Its Turn

The neighbors on Cochran Road handled the heaviest detour load. For most of a year, all northbound Carpenters Grade traffic was sent onto their road. The city made that road a promise early on. The Daily Times reported that once Carpenters Grade reopened in both directions, the city would pay the Blount County Highway Department's costs to repave and restripe Cochran.

The October reopening triggers that promise. The meeting where the plan was explained was held by Blount County Highway Superintendent Jeff Headrick for county residents, even though the project belongs to the city. That makes the Highway Department the natural contact for Cochran residents with questions about the repaving.

Driving the Corridor Between Now and January

Two-way traffic is back, and the corridor is still an active work zone. Some practical notes for the coming weeks:

  • Expect flaggers. The city says the remaining roadway and path work will sometimes need flagging around crews or equipment.
  • The temporary signal at Cross Creek Drive was always meant to be short-term. The city's Phase III plan says two-way traffic returns as the project nears completion, and at that point the temporary signal comes out.
  • Turn limits at subdivision exits were part of Phase III. Under that plan, Cross Creek, Oxford Hills and Knightsbridge were right-turn only onto Carpenters Grade, and the Villas at Carpenters Grade, Legacy Court and Kirkland Estates were left-turn only. Follow whatever the signs at your entrance show on the day you drive.
  • Check the project page. The city posts updates every two weeks on its Carpenters Grade project page.
  • Call the contractor's hotline about your driveway or property. Cleary Construction runs a 24/7 line at 1-800-972-1823 with no automated menu and a guaranteed callback. Reference project number 24411.
  • For anything else, Maryville Engineering and Public Works is at 865-273-3500.

The city's project timeline had targeted year-end 2026 for completion and said it was optimistic about finishing before the January 14, 2027 contract date. Either way, the path, the signal and the Cochran repaving are the last items left on a project first planned in 2009.

If Carpenters Grade is part of your daily drive and you're wondering what the finished corridor could mean for your home's value, or you're thinking about a move nearby, the team at MR10 Realty would be glad to talk it through over coffee. You'll find more on the area on our Maryville neighborhood page, and when you're ready, we're one call away.